Pressure Equipment: Art.71 TU 81/08

The periodic verifications on pressurised systems are regulated by Art.71 of the Italian Legislative Decree 81/08 and by the Ministerial Decree 329/04 which defines the methods for commissioning, operating, testing safety accessories, making repairs and modifications to equipment and pressurised systems defined as GVR – Gas, Vapore, Riscaldamento (Gas, Steam, Heating). The employer can consult not only Public Authorities (INAIL- Italian National Institute for Accident Insurance in the Workplace/ASL -Local Public Health Authority), but also qualified Private Subjects

The periodic verifications are intended to protect the health and safety of workers, more specifically ascertaining:

  • conformity of the pressurised equipment in terms of methods of installation as specified in the manufacturer’s usage and maintenance manual;
  • the state of preservationof the equipment and the maintenance of the safety conditions required;
  • the efficiencyof the safety and control devices of the equipment or the pressurised system by conducting operational tests.

ECO PROVIDES, FREE OF CHARGE, THEIR CLIENTS WITH AN ONLINE MANAGEMENT PORTAL TO MONITOR THE DEADLINES AND TO CHECK THE STATUS OF THE DOCUMENTATION RELATIVE TO THEIR MACHINERY.

WHAT MUST THE EMPLOYER DO?

  1. VERIFY THE COMMISSIONING: The Italian Ministerial Decree 329/04 requires that after having installed the equipment, the Employer must request that INAIL verify the Commissioning and Start-up, if it should fall under the field of application of the same; in case of equipment already excluded from the verification of the consignment, the Declaration may be completed and filed directly (see point 2).
  2. DECLARATION OF THE COMMISSIONING: Once the report of the Commissioning Verification has been obtained, the equipment must be declared to INAIL by means of a special section for the issuing of the registration on the CIVA portal (for the Certification and Verification of Systems and Equipment).
  3. FIRST PERIODIC CONTROL: Once the first period has passed (2 or 3 years, depending on the fluid), request, by means of the CIVA portal, that INAIL conduct the first of the routine controls, entering the name of ECO Certificazioni.
  4. PERIODIC CONTROLS: Upon passing of the successive deadline, contact ECO Certificazioni directly for routine controls.